Blue Owl Leads $2.4B GPU Loan for IREN's Mackenzie Campus

Blue Owl-led funds back a $2.4B, 9.0% fixed-rate GPU loan for IREN's Mackenzie campus. How it works, and why it costs more than IREN's Microsoft loan.

Olivetti-style cover reading Blue Owl $2.4B for IREN GPUs, with a server rack, a coin stack and the words Mackenzie, B.C., 9.0% fixed rate
Olivetti-style cover reading Blue Owl $2.4B for IREN GPUs, with a server rack, a coin stack and the words Mackenzie, B.C., 9.0% fixed rate

Funds managed by Blue Owl Capital have led a $2.4 billion financing that lets IREN Limited buy Nvidia Blackwell Ultra GPUs for its Mackenzie data center campus in British Columbia, Canada. IREN disclosed the deal in its fiscal 2026 results on August 27, 2026, and Blue Owl announced it the next day.

The deal is a loan backed by the GPUs themselves. IREN's annual report says the debt is secured by a first-priority security interest in the financed equipment, and that IREN Limited guarantees the borrower's payment obligations.

The terms

According to Blue Owl's announcement, the financing comprises a $1.2 billion senior secured term loan and $1.2 billion of senior secured notes. Proceeds fund IREN's purchase of "air-cooled NVIDIA Accelerated Computing Infrastructure including NVIDIA Blackwell Ultra GPUs" for Mackenzie.

  • Lenders: IREN's results release describes the $2.4 billion as "led by Blue Owl and Pacific Investment Management Company LLC, as adviser to certain investors."
  • Rate: IREN's results give a 9.0% fixed rate. Its Form 10-K says both the term loan and the notes bear interest at a fixed 9.0% per year.
  • Term: The 10-K says each borrowing and note issuance matures 30 months after its funding date, with principal amortizing on set schedules. The agreements are dated August 25, 2026. The filing also says IREN expects to take delivery of the financed equipment in stages through December 31, 2026.
  • Draws: Blue Owl says the facility funds equipment "in tranches over a defined draw period, allowing capital to be deployed alongside the delivery and commissioning of hardware."
  • Coverage: IREN says the facility "funds 90% of associated GPU capex" and, "together with customer prepayments, provides funding in excess of GPU capex, supporting other data center capex requirements."
Panel comparing IREN's two GPU financings: the .4B Blue Owl-led Mackenzie loan at a 9.0% fixed rate and the .6B Microsoft contract financing at 6.0%

What 9% means next to IREN's Microsoft loan

IREN runs two kinds of GPU debt. Its results list a "$3.6bn investment grade GPU financing for Microsoft contract at 6.0%," which, together with prepayments, funds 96% of the associated GPU capex. The Blue Owl deal sits in a separate bucket: "new $2.8bn GPU financings supporting non-investment grade customer deployments," of which the $2.4 billion is the largest part.

The gap is 3 percentage points. As a rough illustration only (not a figure from IREN), simple annual interest on a fully drawn $2.4 billion would be about $216 million at 9.0%, versus about $144 million at 6.0%. Actual interest depends on how much is drawn and when, and on amortization. IREN's own labels tie the 6.0% financing to its investment-grade Microsoft contract and the 9.0% deal to non-investment-grade customer deployments.

Who said what

IREN chief financial officer Anthony Lewis said in Blue Owl's release that "customer demand for AI compute is accelerating, and we are scaling rapidly to meet it." Nvidia's Nico Caprez, vice president of global AI infrastructure growth, called the deal "another great proof point" and "a repeatable model for financing AI infrastructure at scale," arguing that CUDA makes "NVIDIA AI infrastructure an investable infrastructure asset class for long-term capital." Blue Owl senior managing director Kurt Tenenbaum said: "This is equipment finance at AI scale, and it demands the same discipline."

Those are the parties' own views.

IREN's business behind the loan

IREN still mines Bitcoin but is shifting to AI cloud services. Its fiscal 2026 results (year ended June 30, 2026) show:

  • AI Cloud Services revenue of $128.8 million, up from $16.4 million in fiscal 2025, while Bitcoin mining revenue was $578.2 million of $707.0 million total.
  • A net loss of $702.6 million, which IREN says was impacted by $638.8 million of non-cash impairments, mainly from retiring Bitcoin mining hardware.
  • "$4bn contracted ARR for 2026 capacity; $1bn ARR operating today," with 2026 capacity "largely sold out."
  • Delivery of "Horizon 1," the first of four 50MW liquid-cooled deployments for Microsoft at Childress, Texas.
  • A data center pipeline of more than 5GW, and new customer signings including Cohere, Perplexity and Figure AI, plus a multi-year contract with an unnamed "leading frontier AI lab."

Mackenzie differs from Childress: the Blue Owl money funds air-cooled equipment, while the Microsoft build at Childress is liquid-cooled. IREN also plans new liquid-cooled deployments at Mackenzie during 2027.

Why it matters

The deal adds to a run of private credit financings for AI hardware. On the same day, we reported that Lambda secured $1 billion in private debt for Nvidia GPUs leased to Microsoft. Debt is among the reasons cited for the 47 US AI data center projects that stalled this year, and Microsoft's cancelled Nscale GPU deal shows contracts can change.

What to watch: how fast IREN draws the facility, whether Mackenzie customers pay as contracted, and whether the 9% rate becomes the going price for GPU loans tied to non-investment-grade customers.