Applied Digital's $5.4 Billion Lease Says the Landlords Now Raise the Rent

An 18-year, 150 MW hyperscaler lease at higher pricing than prior contracts, signed by a company worth less than the deal: what Applied Digital's announcement reveals about who holds pricing power in AI infrastructure.

Applied Digital's $5.4 Billion Lease Says the Landlords Now Raise the Rent

An 18-year term, 150 megawatts of critical IT load, roughly $5.4 billion of contracted revenue, and, in the company's own phrasing, "improved commercial terms over our prior leases, including higher pricing." That last clause is the one worth reading twice. Applied Digital announced on Monday November 23 that it signed a new lease with a tier-one, investment-grade hyperscaler whose name it did not disclose, and the disclosure it could make, that the rent per megawatt went up, says more about the state of the AI infrastructure market than the headline number does.

The arithmetic of the deal

A prairie data center campus of windowless buildings under power lines with an open padlock in the foreground

The base term runs 18 years with renewal options that stretch the relationship to 33 years and lift the contract's value to roughly $12.7 billion if every option is exercised. Divided out, the base term works out to about $2,000 per kilowatt of critical IT load per year, at a site whose capacity deliveries are not expected to begin until the first half of calendar 2028.

Two scale notes make the deal stranger than it first appears. The $5.4 billion figure is about 1.6 times Applied Digital's entire equity market value, which sat near $3.4 billion even after Monday's 14% pop. And the stock remains down roughly 59% year to date with the surge included, a reminder that the market has spent 2026 marking AI-infrastructure developers down even while they sign contracts.

With this lease, Applied Digital's totals cross 1.6 GW of contracted critical IT load, 2.2 GW of grid-connected peak load, and above $41 billion of base-term lease revenue, up from the roughly $36 billion disclosed in its fiscal 2026 Form 10-K. About 75% of that contracted base is now attributable to investment-grade customers, a number the company flags because the remaining quarter is where the credit risk lives: the largest earlier tenant was CoreWeave, whose leases at the Polaris Forge 1 campus total around $11 billion.

How the build gets paid for

Applied Digital's funding stack for the new lease is first-in equity from its balance sheet and its $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing secured against the long-term lease itself. CFO Saidal Mohmand told the market the remaining project financing for Delta Forge 1 and Polaris Forge 3 is expected in the first quarter of calendar 2027, with Delta Forge 2 following in the second quarter. Delivery timing, the company says, depends on development milestones, utility arrangements and regulatory approvals, which in late 2026 is the honest way to say the binding constraint is the electrical grid, not the construction crew. An 18-year lease signed for capacity that arrives, if all goes well, in 2028 is a hyperscaler paying for energy it cannot yet switch on.

Why "higher pricing" matters more than the headline

A rolled lease scroll beside transmission pylons and a scale weighing a lightning bolt

Every other layer of the AI stack has a public price war. Model APIs have posted per-token cuts for two straight years, and inference storefronts compete on markup. The physical layer is moving the other direction. Lease rates are rising on signed contracts, take-or-pay commitments are being locked 18 years out, and the landlord with a grid connection and a shovel-ready site holds the leverage. That inversion has been building all quarter on this site's watchlist: utilities are negotiating how to meter AI load onto grids that cannot absorb it quickly, memory makers have repriced entire server lines amid a DRAM and NAND squeeze, and trade enforcement is reshaping who can rent GPUs to whom. An undisclosed tenant agreeing to pay above prior contracted rates, decades in advance, is the same story told from the supply side.

There is a second signal in the customer mix. The tenant is investment grade, and management keeps scoring how much of its book is. CoreWeave, the largest named tenant in the portfolio, is a company whose ability to pay on an 18-year clock depends on its own financing chain. A hyperscaler signs an 18-year lease on the strength of its cash flow, and takes a 150 MW block at a higher rate than its last one did. Whatever else the 2026 correction did to AI infrastructure equities, it did not change what the biggest buyers are willing to prepay.